Tos II Case Progresses
05/25/17 Filed in: High-Speed
Rail
A hearing was held on
April 26 on CHSRA’s Demurrer. The Court’s tentative
ruling denied the motion for preliminary
injunction and sustained the demurrer. At the hearing,
the Court adopted the ruling on the motion for
preliminary injunction, and took the demurrer
under submission. The final ruling adopted the tentative ruling
sustaining the demurrer, effectively knocking the
case out of court, but granted leave to amend the
Petition.
Plaintiffs filed a Second Amended Petition on May 25, in response. After the announcement of the Federal Transit Administration grant to Caltrain for its Electrification Project in May, 2017, the Director of the Department of Finance issued a letter authorizing CHSRA to obligate $713 million in bond funds for Caltrain.
Plaintiffs filed a Second Amended Petition on May 25, in response. After the announcement of the Federal Transit Administration grant to Caltrain for its Electrification Project in May, 2017, the Director of the Department of Finance issued a letter authorizing CHSRA to obligate $713 million in bond funds for Caltrain.